BMW AG, Munich, Germany

Powertrain test facilities FIZ, BA 6.2

Project facts

Year

2005

Duration

6 years

Competences

Turnkey building services engineering

Technical data:

  • 37 engine/transmission test benches incl. 3 climatic chambers, 2 of them with height simulation
  • 100 aggregate and component test benches
  • Gross floor area approx. 40.000 m²
  • Building height approx. 27 m
  • 6 floors + roof structure
  • 3 test bench levels with steel cells for internal combustion engine operation
  • 1 test bench level in solid construction (acoustic test benches)
  • 1 central building services area
  • 2 building services levels (basement and 5th floor)
  • Cooling tower capacity approx. 16 MW
  • Chilled water capacity approx. 8 MW
  • Fuel storage 290,000 liters (incl. BA 6.1)

Ready to turn your idea into reality with SBI WBI?

Together, we turn your idea into a true success project.

Ready for the next step? Inquire now!

Similar References

Get a personal insight into the work of SBI WBI.

Climatic wind tunnel for the first wind tunnel center in Southwest China
CAERI, Chongqing, China
Building T24 “Physikum” – Modules A, B, C, D and E
Audi AG, Ingolstadt, Germany
Driving simulator
FKFS, Stuttgart, Germany